Nexus Point Project Update – July 2019

Following April’s update, we are delighted to share with you the latest build progress for Nexus Point.
Over the past few months, excellent progress has been made on-site, the decoration works have been completed on apartments down to level 2 and are progressing well on the 1st and 2nd floors.
Carpets have been installed to apartments down to level 4 and the corridor decorations have been complete on levels 7 & 8 with plans to complete this in the coming months.

COMING UP NEXT
The construction company are currently working on the final decoration, snagging and rendering works to the external walls and are working on final commissioning for apartments.
Phased completions are anticipated to commence from October 2019. We are providing these dates as guidance only and are subject to change in line with the build program. We will keep you updated with any changes in future project updates. Our Customer Care Team are on hand to answer any questions you may have and to ensure you are kept fully informed throughout the build period.
Nexus Point at a glance
A beautiful development of 85 luxury studio, one and two-bedroom apartments in the established Birmingham suburb of Erdington, just five miles from the city centre.
With excellent transport links, Nexus Point is an ideal solution for young professionals that are looking for an affordable price tag and a convenient location without sacrificing on quality. This high-end development offers easy access to the M6, Birmingham International Airport and the wider rail network connected to Birmingham itself.