SGUV Project Update – May 2019

Following March’s update, we are delighted to share with you the progress for St George’s Urban Village.
The kitchen install works at Albion House and Camden House are ongoing with final works to the commissioning and testing of the lifts at Albion House. Canopies and balconies have been installed at Carver House, Tenby House and Dayus House and balcony instalments have commenced at Camden House.
Final test and commission works are currently being carried out at Summer House and the final decoration works & carpet installations are in progress. Lift installations at Moreton House are ongoing and the internal flooring and stairs have been installed at Tenby Street Townhouses.
Completion will commence from July 2019 and will be a phased handover/completion process. Our Customer Care Team are on hand to answer any questions and to ensure you are kept fully informed throughout the build period. Email [email protected] with any enquiries.
SGUV at a glance
SGUV is a prime Birmingham buy-to-let development set to deliver 304 spacious new homes within walking distance of Birmingham New Street. Just 900m from St Paul’s Square, SGUV will represent Birmingham’s largest-ever residential development – a visionary £100 million scheme that will deliver a total of 596 new homes to the city’s celebrated Jewellery Quarter.
The development builds on Birmingham’s need for high-quality city living options, offering a dynamic community at the heart of the artisan Jewellery Quarter.