The Grand Exchange Update – April 2023

Further to our previous update, the development of The Grand Exchange in Bracknell is progressing well.

Window installation, balcony steelwork and installation has been completed throughout the development.

The Juliet balcony installation is progressing in conjunction with the removal of the scaffolding.

Internal works are progressing including decoration, tiling, kitchen installation, sanitary ware, and joinery.

Lifts are also installed, and the communal areas are progressing including the boarding of the wellness areas and reception.

Completion is anticipated mid-2023.

We are providing this date as a guidance only and it is subject to change in line with the build program.

You can find out more about The Grand Exchange and it’s exclusive resident-only amenities below.

Find Your Perfect Apartment in Bracknell

Explore Developments

Ready to occupy

No.1 Thames Valley

Bracknell

1 Bedroom Apartments, Studio

Prices From

£199,950

Right Arrow

Ready to occupy

The Metalworks

Slough

1 Bedroom Apartments, 2 Bedroom Apartments

Prices From

£240,000

Right Arrow

Final Units Remaining

The Grand Exchange

Bracknell

1 & 2 Bedroom Apartments, 1 Bedroom Apartments, 2 Bedroom Apartments

Prices From

£300,000

Right Arrow

Ready to occupy

105 Broad Street

Birmingham City Centre

2 Bedroom Apartments

Prices From

£252,950

Right Arrow