100 Kensington February Construction Update
BUILDING 2: THE ORIA MAKES GREAT PROGRESS Construction continues to advance across the development. Structural works are progressing upward, with the concrete pour currently reaching Level 17. Containment is complete up to Level 3 and the building’s façade is taking shape as installation is progressing well. At ground level, reinforcement works are nearing completion, complementing […]
100 Kensington November Construction Update
Block 2 – The Oria Exciting milestones are being reached as The Oria continues to take shape! The staircase linking Levels 3 and 4, and Levels 4 and 5 is now complete. Preparations are underway for the installation of the exterior cladding. The surveying engineers will begin work in early November, with installation planned to […]